Many times, when companies decide to transition from outdated legacy systems to a central ERP platform, the result is sweet success. Unfortunately, that wasn’t the case for Hershey. 

Though it’s been more than 25 years since Hershey’s ERP failure, there are still many valuable lessons we can glean from it.

If you’re planning your own implementation, it helps to know where this company went wrong and how you can avoid a similar fate, so let’s look at some of the major issues. 

Contemplating litigation?

We have multiple software expert witnesses available for provision of reports, depositions, and testimonies.

Hershey’s ERP Failure: A High-Level Overview

In 1996, Hershey decided it was time to replace its legacy IT systems with an integrated ERP environment. In all, the platform consisted of three main components:

As you might expect, this was a complex implementation from the very beginning. Though the recommended timeline was four years, Hershey decided to expedite the project. They wanted it done in just 30 months, so it could go live before the projected Y2K bug was speculated to take place. 

The official cutover was scheduled for July 1999, which wasn’t an ideal time for the company to transition onto a new software platform. Hershey receives the bulk of its holiday orders in late summer, and it’s one of the company’s busiest periods of the year.

Not only did executives vastly underestimate the work required to get all systems live by that time, but they also failed to consider how imperfect deliveries would affect their bottom line. 

To juggle the scheduling demands, project leaders took shortcuts and cut corners where possible. This included shortening the testing phase.

4 Lessons Learned From Hershey’s ERP Failure

Where did this project veer off track, and why did those missteps have such dire consequences? Let’s look at a few critical lessons learned from the failed ERP implementation at Hershey.

1. Don’t Rush Systems Testing

If there’s any ERP implementation phase that should be preserved to the greatest extent possible, it’s systems testing. This is an essential part of the journey, and you can’t expedite it simply to meet unrealistic timelines. 

Testing is your opportunity to identify any known errors within your data, processes, and system integrations. Rushing it could mean allowing minor problems to slip through the cracks, where they grow into bigger problems. 

If you need to move back your cutover date to accommodate thorough testing, then do so. It isn’t worth the risks you incur by pressing forward, even if you save time or money in the short-term. 

We recommend simulating realistic operating conditions during your testing phase. Invest in the resources required to help testers feel like they’re using the software in an authentic business environment. This gives them the opportunity to identify as many critical issues as possible. 

2. Allow Plenty of Time

With an investment as sizable as an ERP system, it’s imperative that you take your time.

While the Hershey project should have taken 48 months, it wrapped in just 30. Had project executives allowed more time for critical activities, like testing, and had they performed stage gate reviews, there’s a good chance they would have caught some of the issues. 

3. Consider a Phased Implementation

In Hershey’s case, the abbreviated timeline was more of an issue than the implementation approach. However, the company’s big bang approach certainly didn’t help matters. 

The company attempted to deploy all three technologies at the same time: ERP, CRM, and SCM. While this approach can sometimes result in a lower project cost, it can also be the business equivalent of biting off more than you can chew – especially if the right resources aren’t in place. 

4. Keep Internal Scheduling Demands in Mind

Another problem that led to the Hershey SAP ERP implementation failure? Business executives, department managers, and end-users were fully occupied around the time the system was scheduled to go live. It was one of the busiest seasons for the company, and they weren’t adequately prepared to devote enough time and resources to key activities, like ERP training.

If team members are busy, communication and collaboration fall by the wayside. In Hershey’s case, the ERP project moved to the back burner, while other endeavors took center stage. 

Avoid ERP Implementation Mistakes

It’s easy to think that since Hershey’s ERP failure happened so long ago, it doesn’t apply to your project today. However, a close look at what went wrong proves that some lessons are timeless.

Looking for expert guidance as you begin your ERP project? Contact our ERP implementation consultants below for a free consultation.

About the author

Avatar photo
William L. Baumann is a senior executive with more than 30 years of experience leading growth, transformation, and market expansion across a broad range of industries, including energy, finance, manufacturing, medical devices, professional services, publishing, and nonprofits. He is recognized for his ability to quickly understand complex business environments, design innovative strategies, and deliver measurable results. William has a proven track record in opening new markets, reengineering organizations, and guiding digital and organizational transformation initiatives. His international experience, including living in China and managing long-term initiatives across Latin America, provides him with a global perspective on leadership, strategy, and growth. Over the course of his career, William has achieved significant business outcomes, including securing multimillion-dollar private equity funding, reengineering sales and service delivery models, and implementing best practices that generated substantial revenue growth. His leadership has driven results such as a 380% increase in consumer loan issuance in a single year and a 174% increase in professional services revenue during strategic transformations. Known for his credibility with boards and senior executives, William excels at aligning stakeholders, communicating value at the highest levels, and mentoring high-performing teams to ensure lasting organizational success. In addition to his professional accomplishments, William is deeply committed to community and nonprofit leadership. He has served on boards spanning hospice care, youth development, and the arts, and has volunteered as an ESL instructor in China and as an instructor and mentor in rehabilitation programs. He is also a published thought leader, contributing articles to industry outlets such as Tech Target and InformationWeek, sharing insights on enterprise technology transformation and lessons learned from complex ERP implementations. William earned a Bachelor of Science in Economics, graduating cum laude from Fairleigh Dickinson University. His career reflects a consistent focus on transformational leadership, measurable impact, and the development of both business and community value. William’s combination of strategic vision, operational expertise, and global experience positions him as a trusted advisor and executive leader capable of delivering sustainable growth and transformational results.

Posts You May Like:

Generative AI Use Cases for Mid-Market Companies

Generative AI Use Cases for Mid-Market Companies

Key Takeaways Generative AI is used in business to accelerate decision-making and reduce manual work. Practical generative AI use cases for mid-market companies include finance close optimization, AI-assisted procurement, and tailored onboarding programs. A...