Businesses are increasingly dependent on ERP software systems to manage their operations, but when these systems fail, the repercussions can be catastrophic.

A recent case of significant failure occurred with Mission Produce, a global leader in avocado distribution. It highlights critical lessons that every organization can learn from.

Today, we will discuss the Mission Produce ERP software implementation failure, explore what went wrong, and extract vital lessons for avoiding similar pitfalls in future IT projects.

An Overview of Mission Produce’s ERP Software Implementation​

In 2022, Mission Produce embarked on a project to upgrade its enterprise software system, aimed at streamlining its supply chain management software, enhancing inventory management, and improving overall efficiency.

The company, which operates across multiple continents, required a robust solution to handle the complexities of global supply and demand.

However, the project was met with challenges when the system went live, resulting in operational disruptions. The company experienced delays in order processing, inventory inaccuracies, and a breakdown in communication between different business units.

These problems culminated in missed delivery deadlines, unsatisfied customers, and financial losses.

Contemplating litigation?

We have multiple software expert witnesses available for provision of reports, depositions, and testimonies.

4 Lessons Learned from Mission Produce’s Software Implementation Failure

The software implementation failure offers four lessons that can help other organizations navigate the complexities of IT projects.

1. The Importance of Thorough Requirements Gathering and Validation

One of the root causes of Mission Produce’s software failure was inadequate requirements gathering. The company failed to fully understand the unique needs of its global operations, leading to a mismatch between the software’s capabilities and the actual business requirements.

For instance, the ERP system’s inventory management module, which was crucial for a company dealing in perishable goods, lacked the necessary features to manage real-time stock levels across multiple locations. This oversight led to discrepancies in inventory data, causing overstocking in some regions and shortages in others.

Additionally, the lack of proper validation of the gathered requirements before development led to the implementation of features that were either redundant or misaligned with the company’s operational workflows.

The Lesson

Our independent ERP selection consultants recommend mapping each requirement to its corresponding business process to ensure nothing is overlooked during development. Comprehensive requirements gathering and validation are essential for the success of any IT project. Organizations must invest time and resources into understanding the specific needs of their business before selecting or developing software solutions.

Key success factors include:

 

  • Engage Stakeholders Early and Often: Involve all relevant stakeholders in the requirements gathering process to ensure that their needs are accurately captured. This includes input from all departments that will interact with the system, ensuring that the final solution meets the needs of the organization.
  • Perform Detailed Requirements Analysis: Conduct a thorough analysis of the gathered requirements to identify potential conflicts, redundancies, and gaps. This process should involve cross-functional teams to ensure that all aspects of the business are considered.
  • Validate Requirements Before Development: Before proceeding with the software development or selection process, validate the requirements through workshops, simulations, or prototypes. This step helps to identify any issues early in the process, reducing the risk of costly errors later on.

2. The Need for a Realistic Project Timeline and Scope

Mission Produce’s project was marred by overly ambitious timelines and scope creep, both of which contributed to its failure. The company underestimated the complexity of the software implementation, leading to a compressed timeline that didn’t allow for adequate testing, user training, or phased rollouts.

Additionally, as the project progressed, new features and capabilities were added to the scope without corresponding adjustments to the timeline or resources. This scope creep placed additional strain on the project team and resulted in the deployment of an unfinished and poorly integrated system.

The Lesson

Organizations must be cautious about expanding project scope and ensure that timelines are achievable. Key strategies for managing timeline and scope include:

  • Set Realistic Timelines Based on Complexity: Develop a project timeline that reflects the complexity of the implementation. Consider factors such as data migration, integration with existing systems, and the need for customizations. Allow sufficient time for each phase, including design, development, testing, and training.
  • Implement Phased Rollouts: Instead of launching the entire system at once, consider a phased rollout approach. This allows the organization to address issues in smaller, less critical areas before moving on to more complex and high-impact modules.
  • Control Scope Creep Through Project Governance: Establish strong project governance that provides a framework for evaluating changes to the project scope. This should include a cost-benefit analysis of the proposed changes, as well as an assessment of their impact on the timeline and resources.

In our software implementation projects, we often advocate for an approach where the core functionalities are delivered first, with additional features rolled out in subsequent phases. This approach helps manage scope and ensures that critical functionalities are thoroughly tested and stable before expanding.

3. The Vital Role of User Training and Change Management

Another critical failure in the Mission Produce project was the lack of adequate user training and change management. The new software system represented a shift from the company’s previous processes, yet employees were not properly trained to use the new system effectively.

This lack of training led to widespread confusion, errors in data entry, and resistance to using the new system. In some cases, employees reverted to using legacy systems or manual processes, which further exacerbated the operational disruptions.

Moreover, there was no structured change management plan in place to help employees transition to the new system. The abrupt switch to the new ERP software without proper guidance and support created a chaotic work environment and eroded employee morale.

The Lesson

Organizations must ensure that employees are well-prepared to use new systems and that there is a structured plan in place to manage the transition. Key strategies include:

  • Develop a Comprehensive Training Program: Create a detailed training program that covers all aspects of the new system, from basic navigation to advanced functionalities. Training should be tailored to different user groups based on their roles and responsibilities within the organization.
  • Prioritize Change Management: Develop a change management plan that addresses the cultural and procedural shifts required by the new system. This plan should include communication strategies, support mechanisms, and a timeline for transitioning from the old system to the new one.
  • Provide Ongoing Support and Resources: Ensure that employees can continue to succeed long after the ERP system goes live. This can include help desks, online tutorials, and refresher training sessions. Continuous support helps to address any issues that arise and reinforces the adoption of the new system.

In our experience, involving end-users in the system design and testing phases can significantly enhance user buy-in and reduce resistance to change. By giving employees a sense of ownership in the new system, organizations can foster a smoother transition and increase the likelihood of successful adoption.

4. The Necessity of Strong Leadership and Governance

The failure of Mission Produce’s software implementation can also be attributed to a lack of strong leadership and governance. The project lacked clear accountability, with no single individual or team responsible for overseeing the entire implementation.

This absence of leadership led to poor decision-making, inadequate risk management, and a failure to address issues as they arose.

The project also lacked effective governance structures, such as steering committees or oversight bodies, that could have provided guidance and intervened when necessary. Without these structures in place, the project drifted off course, and problems were allowed to escalate unchecked.

The Lesson

Strong leadership ensures that the project stays on track and that issues are addressed promptly, while governance structures provide oversight and accountability. Key success factors include:

  • Appoint a Dedicated Project Leader: Assign a dedicated project leader with the authority to make decisions and the responsibility to oversee the entire implementation. This individual should have a clear understanding of the project’s objectives and be empowered to take corrective actions when necessary.
  • Establish Governance Structures: Create governance structures, such as steering committees or project management offices (PMOs), to provide oversight and guidance. These bodies should be composed of representatives from key business units and have the authority to make decisions on project-related issues.
  • Regularly Review Project Progress: Implement regular project reviews to assess progress, identify risks, and address any emerging issues. These reviews should be conducted by both the project team and the governance bodies to ensure that the project remains aligned with its objectives.

In our role as ERP consultants, we often recommend the establishment of a Project Management Office (PMO) to oversee large-scale software implementations. The PMO can provide the necessary structure, resources, and expertise to ensure that the project is managed effectively and that any issues are addressed in a timely manner.

Ensuring Success in Software Implementation Projects

The implementation failure at Mission Produce serves as a cautionary tale for organizations embarking on complex software implementation projects.

By applying these lessons, your organization can better navigate the challenges of software implementation and increase your chance of success.

If you are planning a software implementation or digital transformation project, our team of business software consultants can help you avoid the common pitfalls and ensure a successful outcome. Contact us below to learn more about how we can support your organization in achieving its strategic objectives.

About the author

Avatar photo
As Director of Panorama’s Expert Witness Practice, Bill oversees all expert witness engagements. In addition, he concurrently provides oversight on a number of ERP selection and implementation projects for manufacturing, distribution, healthcare, and public sector clients.

Posts You May Like:

How to Select a Tier 1 ERP System: 5 Tailored Tips

How to Select a Tier 1 ERP System: 5 Tailored Tips

Every year, we conduct an independent analysis of the Tier 1 ERP vendors. The analysis, known as Clash of the Titans, is based on data we collect from organizations that have implemented SAP, Oracle, Microsoft, or Infor products. As we release 2025 Clash of the...

Fear of IT: How to Calm Workplace Tech Anxiety Among Employees

Fear of IT: How to Calm Workplace Tech Anxiety Among Employees

Among those who fear the unknown (almost everyone), the thought of digital transformation can be a source of great anxiety. When technological change threatens to disrupt workplace roles, employees may feel uncertainty about their future, and uncertainty tends to...